Commissioning Management – Milan, Italy

Loop Engineering produced a commissioning strategy for HSBC server room in their new offices in Milan, Italy. Loop Engineering attended site to witness and sign off the working of the server room.

Works included:

  • Shutting down the generator to ensure the UPS acknowledged the main supply had gone down and the generator was supplying the load and bringing the mains back on and ensuring the UPS also picked this up.
  • Load tests on UPS
  • AC units testing
  • BMS alarms testing
  • Fire alarm system testing, where alarms were simulated to ensure the correct sequence of alarm was followed and the correct notifications were shown on the main fire alarm panel and also on the landlords fire alarm panel.